1500 MW CCGT independent power plant project
Excavation, backfilling and compaction for Power Unit and Steam Turbine in construction of "Independent Power Project CCGT 1500 MW" in Shirin city, Syrdarya region. Client: "ACWA Power", General Contractor: "China Gezhouba Group International Engineering Co, LTD":
1) Excavation, backfilling and compaction pits for Power block and Steam turbine,
2) Earth works in AIS area (500 kv, 220 kv.), control building “Uzbekistan Sirdarya 1500 MW CCGT Independent Power Project”,
3) Installing “Temporary drainage channels”,
4) Transporting backfill material: gravel, crushed stones and sand from quarries. (Gravel – 100000 m3, crushed stones – 25000 m3, sand – 20000 m3),
5)Breaking down 800 mm concrete piles according to the elevation,
6) 2021 y. Construction of Owner’s Temporary Site Office and Camp lighting poles of “Uzbekistan Sirdarya 1500 MW CCGT Independent Power Project”,
7) Construction of car parking and canteen for Owner’s Temporary Office of “Uzbekistan Sirdarya 1500 MW CCGT Independent Power Project”,
8) Landscaping